Toulouse (31)
Construction of a 63 kV electrical delivery substation at Toulouse University Hospital.
Special attention was paid to blending the building into its urban surroundings. Project subject to approval from the French architectural review board (ABF).
Owner: CHU de Toulouse
Budget: €5.32m
Assignment: Competitive bid – Complete design services and construction supervision
Years: 2021 – 2022